MT1000A Installation and Operation Manual Chapter 2 Installation and Setup
Installation and Setup 2-3
2.5 Installation and Setup
To install MT1000A:
1. Set the internal switches.
2. Connect MT1000A’s various interfaces in the order listed here.
This module may include Class A or Class 1 lasers. For your safety:
Do not look directly into the optical connectors while the module is
operating. Remember that the MT1000A starts operating as soon as it is
powered.
Do not attempt to adjust the laser drive current.
The use of optical instruments with this product will increase eye hazard. Laser
power up to 1 mW at 850 nm and at 1310 nm could be collected by an optical
instrument.
Use of controls or adjustment or performing procedures other than those
specified herein may result in hazardous radiation exposure.
WARNING: The laser beam is invisible.
Setting the Internal Switches
Prior to MT1000A installation, check the positions of its internal switches. If
necessary, change the settings in accordance with the specific requirements of
your application.
Opening MT1000A Case
To open MT1000A and access reach the internal switches:
1. Disconnect all the cables connected to MT1000A.
2. Unscrew the eight screws on the top panel.
3. Unscrew the screws on both side panels.
4. Remove the top cover.